Our school district continues to be one of the 3rd fastest growing districts in the Region. Over the past few years, we have been growing 8 - 12% annually. MVISD serves approximately 11,200 with 10 Campuses. We have two High Schools, two Middle Schools and six Elementary Schools.
To help keep up with the growth, the MVISD community passed two bond elections:
May 2023 Bond for $376 million included the following projects:
-
-
-
-
- High School #2 (Creekview HS opened August 2026)
- Safety & Security Updates
- Traffic Improvements
- Medina Valley HS Agricultural & JROTC Facility (opened August 2026)
- Land Purchases
-
-
-
May 2024 Bond for $290 million included the following projects:
-
-
-
-
- Middle School #3 (Lucas Creek Middle School under construction)
- Elementary #7 (Design completed, Construction Contract awarded Fall 2026)
- Elementary #8
- Medina Valley HS Physical Education Facility Improvements (in progress)
- Safety & Security Updates
- Land Purchases
-
-
-
Check out our Video Series
Bond Dollars at Work
(July 2026, Feb.2026, Aug.2025, Nov.2024 & Aug.2024)
CREEKVIEW HIGHSCHOOL - Opened Fall 2026
Medina Valley High School AG+JROTC Bldg. - Opened Fall 2026
Medina Valley Middle School #3 - Fall 2027 - Lucas Creek Middle School under construction
MVISD Elementary School #7 - Fall 2028
Bond Dollars at Work : July 2026
This is the 5th in our video series to see the latest updates and facility improvements currently underway at Creek View High School, MVISD Middle School #3, MVISD HS Ag/JROTC & Stadium Enhancements, with planned ribbon cutting ceremonies for Creek View HS (July 2026) & MVHS Ag/JROTC projects (August 026).
https://www.youtube.com/watch?v=w_fGWccAit8
* * * * * * * * * * * * *
Bond Dollars at Work : February 2026
This is the 4th in our video series to see updates at Middle School #3, the completion of Creek View High School, and how all bond projects are staying on schedule.
https://www.youtube.com/watch?v=sjeWJgy2cbM
* * * * * * * * * * * * *
Bond Dollars at Work : August 2025
This is the 3rd in our video series to show construction progress of Creek View High School to the new Agricultural / JROTC buildings at MV High School, to our progress of Middle School #3 & more.
* * * * * * * * * * * * *
Bond Dollars at Work: November 2024
This is the 2nd in our video series to show construction progress.
https://www.youtube.com/watch?v=no3IRiQKkcQ
* * * * * * * * * * * * *
Bond Dollars at Work: August 2024
We hope this video series helps to keep you updated on the progress of those bond projects, so that you can see your bond dollars at work.
https://www.mvisd.com/apps/news/article/1956423
For more information stay tuned to MVISD Home Page https://www.mvisd.com/ , search topic FAST GROWTH, for news/updates, as we continue to build towards the future for our kids.
Medina Valley ISD